Construction progress
Follow the development of the project through monthly work updates. Monitor the completion of each construction stage and stay current with the development.
Phase 1
Consists of 4 residential buildings (B+GF+2F+R), accommodating 10 apartments each
Phase 2
Consists of 4 residential buildings (B+GF+3F+R), accommodating 17 apartments and 3 commercial spaces each
Phase 3
In design phase












October 2026
October 2026










September 2026
- Partition walls (2nd, 3rd & setback floor) - 75%
- Electrical installations (ground, 1st & 2nd floor) - 75%
- Electrical installations (3rd & setback floor) - 50%
- Plumbing and heating (ground – setback floor) - 50%
- Aluminum exterior carpentry - 25%
September 2026
- Partition walls (2nd, 3rd & setback floor) - 75%
- Electrical installations (ground, 1st & 2nd floor) - 75%
- Electrical installations (3rd & setback floor) - 50%
- Plumbing and heating (ground – setback floor) - 50%
- Aluminum exterior carpentry - 25%










August 2026
- Masonry: Floors 1, 2, and 3 (100%)
- Partition walls: Ground floor and 1st floor (100%) | Floors 2 and 3 (75%) | Setback floor (50%)
- Electrical installations: Ground floor and 1st floor (75%) | 2nd floor (50%) | 3rd floor and setback floor (25%)
- Plumbing and heating: All levels, from the ground floor to the setback floor (25%)
August 2026
- Masonry: Floors 1, 2, and 3 (100%)
- Partition walls: Ground floor and 1st floor (100%) | Floors 2 and 3 (75%) | Setback floor (50%)
- Electrical installations: Ground floor and 1st floor (75%) | 2nd floor (50%) | 3rd floor and setback floor (25%)
- Plumbing and heating: All levels, from the ground floor to the setback floor (25%)




July 2026
July 2026










June 2026
- Setback floor slab (reinforcement and pouring): 100%
- Masonry: Ground floor and floors 1, 2, 3 – 75%; Setback floor – 50%
- Partition walls: Ground floor and floors 1, 2 – 50%; 3rd floor – 25%
June 2026
- Setback floor slab (reinforcement and pouring): 100%
- Masonry: Ground floor and floors 1, 2, 3 – 75%; Setback floor – 50%
- Partition walls: Ground floor and floors 1, 2 – 50%; 3rd floor – 25%
















May 2026
- Slab pouring over 3rd floor - 100%
- Reinforcement of columns and shear walls, setback floor - 100%
- Pouring of columns and shear walls, setback floor - 100%
- Slab reinforcement over setback floor - 75%
- Slab pouring over setback floor - 50%
- Masonry: Ground floor - 75%
- Masonry: 1st floor - 75%
- Masonry: 2nd floor - 50%
- Masonry: 3rd floor - 25%
May 2026
- Slab pouring over 3rd floor - 100%
- Reinforcement of columns and shear walls, setback floor - 100%
- Pouring of columns and shear walls, setback floor - 100%
- Slab reinforcement over setback floor - 75%
- Slab pouring over setback floor - 50%
- Masonry: Ground floor - 75%
- Masonry: 1st floor - 75%
- Masonry: 2nd floor - 50%
- Masonry: 3rd floor - 25%




















April 2026
- Slab pouring over 2nd floor - 100%
- Reinforcement of columns and shear walls over 3rd floor - 100%
- Formwork for columns and shear walls over 3rd floor - 80%
- Pouring of columns and shear walls over 3rd floor - 60%
- Slab reinforcement over 3rd floor - 40%
- Slab formwork over 3rd floor - 20%
- Masonry: Ground floor - 40%
April 2026
- Slab pouring over 2nd floor - 100%
- Reinforcement of columns and shear walls over 3rd floor - 100%
- Formwork for columns and shear walls over 3rd floor - 80%
- Pouring of columns and shear walls over 3rd floor - 60%
- Slab reinforcement over 3rd floor - 40%
- Slab formwork over 3rd floor - 20%
- Masonry: Ground floor - 40%










March 2026
- Slab reinforcement over 1st floor - 100%
- Slab formwork over 1st floor - 100%
- Slab pouring over 1st floor - 80%
- Reinforcement of columns and shear walls over 2nd floor - 60%
- Formwork for columns and shear walls over 2nd floor - 40%
- Pouring of columns and shear walls over 2nd floor - 20%
March 2026
- Slab reinforcement over 1st floor - 100%
- Slab formwork over 1st floor - 100%
- Slab pouring over 1st floor - 80%
- Reinforcement of columns and shear walls over 2nd floor - 60%
- Formwork for columns and shear walls over 2nd floor - 40%
- Pouring of columns and shear walls over 2nd floor - 20%








February 2026
- Reinforcement of columns and shear walls over ground floor - 100%
- Formwork for columns and shear walls over ground floor - 80%
- Pouring of columns and shear walls over ground floor - 60%
- Slab reinforcement over 1st floor - 40%
- Slab formwork over 1st floor - 20%
February 2026
- Reinforcement of columns and shear walls over ground floor - 100%
- Formwork for columns and shear walls over ground floor - 80%
- Pouring of columns and shear walls over ground floor - 60%
- Slab reinforcement over 1st floor - 40%
- Slab formwork over 1st floor - 20%








January 2026
- Slab reinforcement over basement - 100%
- Slab formwork over basement - 100%
- Slab pouring over basement - 100%
- Reinforcement of columns and shear walls over ground floor - 60%
- Formwork for columns and shear walls over ground floor - 30%
January 2026
- Slab reinforcement over basement - 100%
- Slab formwork over basement - 100%
- Slab pouring over basement - 100%
- Reinforcement of columns and shear walls over ground floor - 60%
- Formwork for columns and shear walls over ground floor - 30%










December 2025
- Concrete pouring for basement walls - 100% completed
- Waterproofing of basement walls - 100% completed
- Slab reinforcement over basement - 90%
- Slab formwork over basement - 80%
- Slab pouring over basement - 50%
December 2025
- Concrete pouring for basement walls - 100% completed
- Waterproofing of basement walls - 100% completed
- Slab reinforcement over basement - 90%
- Slab formwork over basement - 80%
- Slab pouring over basement - 50%






November 2025
- Basement foundation reinforcement - 100% completed
- Basement wall reinforcement - 100% completed
- Concrete pouring for basement foundations - 100% completed
- Concrete pouring for basement walls - 80% completed
- Waterproofing of basement walls - 70% completed
November 2025
- Basement foundation reinforcement - 100% completed
- Basement wall reinforcement - 100% completed
- Concrete pouring for basement foundations - 100% completed
- Concrete pouring for basement walls - 80% completed
- Waterproofing of basement walls - 70% completed








October 2025
- Basement foundation reinforcement - 80% completed
- Basement wall reinforcement - 70% completed
- Concrete pouring for basement foundations - 80% completed
- Concrete pouring for basement walls - 60% completed
- Waterproofing of basement walls - 30% completed
October 2025
- Basement foundation reinforcement - 80% completed
- Basement wall reinforcement - 70% completed
- Concrete pouring for basement foundations - 80% completed
- Concrete pouring for basement walls - 60% completed
- Waterproofing of basement walls - 30% completed






September 2025
- Leveling concrete pouring - 100% completed
- Basement foundation reinforcement - 60% completed
- Basement wall reinforcement - 40% completed
- Concrete pouring for basement foundations - 50%
- Concrete pouring for basement walls - 20%
September 2025
- Leveling concrete pouring - 100% completed
- Basement foundation reinforcement - 60% completed
- Basement wall reinforcement - 40% completed
- Concrete pouring for basement foundations - 50%
- Concrete pouring for basement walls - 20%












August 2025
- Excavation - 100% completed
- Leveling concrete pouring - 80% completed
- Basement foundation reinforcement - 20% completed
August 2025
- Excavation - 100% completed
- Leveling concrete pouring - 80% completed
- Basement foundation reinforcement - 20% completed








July 2025
- Started setting up the construction site (sau Started site organization setup)
- Completed approximately 15% of the excavation
July 2025
- Started setting up the construction site (sau Started site organization setup)
- Completed approximately 15% of the excavation
Official sales agent
The images shown on this website are for illustrative purposes only and are intended solely for marketing presentation. These visuals are non-binding and do not establish contractual obligations. Furniture, interior decor, or landscaping features (vegetation, outdoor fittings, etc.) are not included in the standard offer and are not delivered with the units. We reserve the right to modify design or technical specifications without prior notice.